Maiden, NC
Confidential Data Center
Project Summary
Rosendin provided electrical construction services for this two-phase, build-to-suit data center for an existing technology client. The project includes over 200,000 GSF of prefabricated concrete walls supporting electrical infrastructure comprised of an uninterruptible power supply system supported by diesel generators. The raised data floor components consist of a prefabricated distribution system to accommodate the client’s layout of electronic equipment, as well as an energy-saving hot air, cooling design. In addition to the data infrastructure, this project included over 8,000 SF of Class A office space.
Sectors
Offices
Services
Value Add
Confidential Data Center
Data Center & Office Space | Prefabricated new construction
Location |
Maiden, NC |
Client |
Confidential |
General Contractor |
Gilbane Building Company and Turner Construction Company |
Duration |
25 Months |
Budget |
$53,488,326 |
Size |
200,000 SF |