Sterling, VA

CyrusOne – Building 1 Sterling Data Center Campus

Project Summary

Rosendin was awarded the electrical contractor role for this beginning phase of CyrusOne’s state-of-the-art data center in Northern Virginia. This stage was fast-track performed using lean construction methods for ground-up construction of Building 1, consisting of 132,000 square feet with 10 megawatts of power. The scope of work included installation of five (5) diesel generators, utility transformers, uninterrupted power source system, electrical switches, and distribution units and miles of cable and conduit.

CyrusOne – Building 1 Sterling Data Center Campus

Building 1 of CyrusOne's leading edge, enterprise-class, data center campus in Northern Virginia.

Location
Sterling, VA
Client
CyrusOne
General Contractor
NOVA Mission Critical CM
Duration
19 Months
Budget
$5,729,313
Size
132,000 SF